| 1 |
29 Sep last day for udeb changes for tc2
|
| 2 |
udebs propigated to testing (rc1 breaks)
|
| 3 |
30 Sep release tc2 (or give up on the idea)
|
| 4 |
string freeze begins
|
| 5 |
start building full CDs for tc2
|
| 6 |
4 Oct full CDs finish building for tc2, are released
|
| 7 |
7 Oct translation uploads
|
| 8 |
last day to upload fixes to packages on initrds
|
| 9 |
8 Oct initrd builds start for rc2
|
| 10 |
21 Oct initrd builds finish (or earlier..)
|
| 11 |
last day for uploads of any udebs or debs for rc2
|
| 12 |
22 Oct udebs propigated to testing (tc1 breaks)
|
| 13 |
full debian freeze probably starts here
|
| 14 |
final netinst and businesscard CD builds
|
| 15 |
begin full CD builds
|
| 16 |
23 Oct testing begins
|
| 17 |
26 Oct full CD builds finish
|
| 18 |
29 Oct web site updates
|
| 19 |
and rc2 release
|